Number of Wells: 1
Well Type: Blind
True Vertical Depth: 19
Screen Length: 650
Total Well Length: 830
This soil vapor extraction well was completed in a
blind borehole at an abandoned refinery site. The site geology
consisted of gravel and sand with minor amounts of fine sand. Well
materials consisted of 6 diameter, slotted steel screen with 6
steel riser casing. Ten-inch diameter HDPE was used as surface
casing from the entry point to a measured depth of 141. The well
was drilled using both bentonite and bio-polymer based drilling
fluids. Development procedures included chemical and physical
treatment methods. At the time of installation, the well was
believed to be the longest soil vapor extraction well completed in a
blind borehole. The well is currently in use and is producing 1,200
scfm.

|